BU 5115 - Operations Management (Spring 2005 TEST 3 Dr. A. Ebrahimi)
Answer 5 out of 7 questions and include Q1.
Each part of question should be answered separately since it would be graded separately. Use copy and paste to word document. As soon as you finish the first question print and hand it in to be graded)
Q1) In your project, as a Operation Manager of a business compare your Strategy Decisions with Hard Rock Cafe Project Manager. (Answer four of the following questions). Each part has 5 points.
Q1a) Explain your mission in compare with
Hard Rock Café.
Q1b) What is the theme of your project in compare with Hard Rock Café?
Q1c) What are your tasks and sub-tasks in compare with Hard Rock?
Q1d) How do you handle crisis in compare to Hard Rock Cafe?
Q1e) How are your employees rewarded in compare with Hard Rock Cafe?
Q1f) How the layout of your business is different from Hard Rock Cafe.
Q1g) How do you deal with Forecasting in compare with Hard Rock Cafe?
Q1h) How globalization is handled in your project compare with Hard Rock
Cafe.
Q2) Answer the following
Q2a) What is Linear Programming? Give an example for an operation manager. (5pts)
Q2b) What is the goals of JIT and What is Lean Production systems? Give an example for each. (5pts)
Q2c) What is Transportation Modeling? Give an example. (5pts)
Q2d) How a multifactor productivity is calculated? Give an example. (5pts)
Q3) Choose CPM or PERT and show the following:
For CPM:
Q3a) Activity table and predecessor table.(4pts)
Q3b) Network diagram. (4pts)
Q3c) Forward pass, calculate Early Start, Early Finish, and Slack. (4pts)
Q3d) Backward Pass, calculate Late Start, Late Finish, and Slack (4pts)
Q3e) Find the Critical Path (4pts)
For PERT: Each part has 4 points.
Q3aP) Show a time table with expected time and variance.
Q3bP) Show the project variance and project standard deviation.
Q3cP) Show the probability of project completion at certain time.
Q3dP) Determine project completion time for a given confidence level.
Q4) Pick two of the Job Priority Rules for Dispatching Jobs (FCFS, SPT, EDD, LPT) and answer the following for four jobs A, B, C, D with given processing time and job due date: Each part has 5 points
Q4a) Calculate the Flow Time and Job Lateness (hint: Use Flow Time to
calculate Lateness)
Q4b) Calculate the Average Completion Time
Q4c) Calculate Utilization
Q4d) Calculate the Average of Lateness
Q4 Extra Credit) Process the above jobs with two work centers. Give your own processing time for each center. Show how many hours it will take for all the jobs to be completed. Use Johnson's Rule to minimize processing time and total idle time. (10pts)
Q5) Answer 4 of the following and each part has 5 points
Q5a) Give three differences between goods and services and give an example for each.
Q5b) Describe Motorola's strategy for Total Quality Management. What are three of the rules?
Q5c) What is Total Quality Management?
Q5d) What is Competitive Advantage?
Q5e) What are five of the ten measures of quality of service?
Q6) Choose MS Project to show any of the following: (20 pts)
Q6a) Precedence table
Q6b) Gantt chart
Q6c) Project network
Q6d) Tracking project progress
Q7) Use Excel to perform any of the following: (20 pts)
Q7a) By using Excel analyze a weighted moving average forecasting for a company of your choice. Provide your own data.
Q7b) Use Excel for Options for Increasing Contribution for three different options (Marketing, Finance/Accounting, OM options) Explain the difference between each option.
Q7c) Use Excel to make calculations for forecasting, for example: MAD, MSE and MAPE for 9 quarters of a company.