OM Class Notes: 3/1/06
Note Takers: Thomas Molesky & Catherine Palma
· What did we do last class?
o Tables
o Diagram
· Network Diagramming
o Timing is given
o Discuss Catherine’s Homework
o Discussed about the way Catherine Diagrams CPM

· CPM




o Calculate the Early Start and the Late Finish
o Example

§ Early – Add
§ Late – Subtract
o Main idea: Find slack by knowing values
· Why do we need to find slack?
o That node is in the critical path
o Determine node that has a slack of zero
§ Can’t play around
· Two values difficult to find ŕ Know these 2
o Early Start
o Late Finish
· Project should not be more than 27 weeks
o Concept
· Two things are the hardest part
o Early Start
o Late Finish
· Chapter 3 focuses on this
o Book
o No book – SEE THE BOOK SITE IN THE POWER POINT SLIDESHOW
· +1 Saeed
·

o Passed time table activity
§ ES + 2 = 2
§ Assumption
If LF = 11, then LS = 9

Activity – LF = 11 – 2 = 9
§ Try to make some sense out of it
· 2 Things
o Early Start & find Late Finish
o Early start is the problem
· 2 Passes
o Forward Pass
§ Early start is difficult
o Backward Pass
· What would be the early start?
o Zero
o ES for the first node isn’t difficult
· The formula of ES
o ES = Max(EF of all immediate predecessors)
· Went over power points
o Ch. 6
o Ch. 3
· If you have LF, what is the late start?
o LF – Activity
STOP @ 9:37 PM