Class Notes: 2/15/06
Note Takers: Catherine & Thomas
· What did we do last time?
o Presentation – by Sara
§ Same food, different portions
§ Rice differentiation
§ Nicole +1
§ Americans eat more than Korea
§ Chicken Sandwich – Spicy à hot
· Today’s Presentation
o Akron
Today
CPM (Critical Path Method)
PERT (Program Evaluation Review Technique) - Lance +1
What to do with these two above? To finish project in a good timely/costly fashion by lowering the cost.
Job can be done simultaneously - Lisa +1
CPM
PERT
Class Assignment:
Project # 2: Use the Critical Path Method to complete a project. Find the critical path. Make up your own project. Use example from book (handouts pg. 54 and pg. 57). PERT will be extra credit.
Handouts will be given
MAKE IT YOUR OWN WITHOUT COPYING - SHOW YOU HAD LEARNED - SITE YOUR SOURCES AS WELL
PERT - Extra Credit
Demo it --> 5 pts - Good experience from a student and got an "A"
NO DUE DATE
Internet References (Google search: “critical path method”):
http://www.netmba.com/operations/project/cpm/
http://hadm.sph.sc.edu/COURSES/J716/CPM/CPM.html
http://www.buildersnet.org/cpmtutor/cpmtutor.html
CPM: 4 words: ES (Early Start), EF (Early Finish), LS (Late Start), LF (Late Finish).
E stands for Early
Early means how early you can start, finish
EF=early finish - Tahidul +1
What does L mean? Late
S means start.
F means finish.
What's the earliest you can start?
What's the latest you can finish?
Node represents an activity
Every node/activity has ES, EF, LS, and LF.
Every node/activity has a completion time.
Immediate predecessor: activities that must be completed before node/activity can start.
Every node can have one before it? Predecessor - Steve +1
Can't start B without A.
2 ways to do CPM:
Forward Pass – start from beginning and compute ES and EF. Backward Pass – start from end and compute LS and LF.
CMP works with a fixed time. Ex. Go to mechanic for 50,000 mile tune-up (they know when the parts need to be replaced).
Know how much it takes - approximate time
Slack – allowable delay. If slack is 0 (zero), it’s in the critical path, any delay will delay whole project.

Can't compromise with these nodes
Learned about slack and compromise
Compromise means:

Compute Slack: 2 ways
LS - ES and LF - EF (result of backward pass minus forward pass). If result is 0, it’s in the critical path.
What is the latest and earliest start?
Each Node:
Name of the node, duration that it takes, ES, EF, LS, LF, Slack
Finding ES (forward pass):
ES = Max(EF of all immediate predecessors)
Look @ maximum of EF - all immediate predecessor
How to find ES - Go to that node & look for the earliest finished
What's the earliest start for each node? Find out when they finish the node before & find the maximum.
EF of each node is calculated within the node itself.
Finding LF (backward pass):
LF = Min(LS of all immediate predecessors)
Mistake in the book about this - student brought it up
What's the latest i can finish? Look @ latest start and look at minimum of it.
Summary
For every node, find earliest start and latest finish.
Critical Path = 0
Find a way to remember it!!!
____________________________________________________________________________________
Director of TLC - Professor Ebrahimi
Project
April 28th, Mid-April
Why changed it this year? Good Friday
Now Professor Ebrahimi will show everything on April 28th.
Professor Ebrahimi plans via memory
Time Slot Example: Delta
Nicole - Previous question +1
________________________
Three you should know
1. Uniqueness/Quality Differentiation
2. Low Cost
3. Response - Ralph & Scott +1
__________________
From pg. 57 in book:
|
Activity |
Description |
Time (weeks) |
|
A |
Build internal components |
2 |
|
B |
Modify roof and floor |
3 |
|
C |
Constructs collection stack |
2 |
|
D |
Pour concrete and install frame |
4 |
|
E |
Build high-temperature burner |
4 |
|
F |
Install pollution control system |
3 |
|
G |
Install air pollution device |
5 |
|
H |
Inspect and test |
2 |
|
|
Total Time (weeks) |
25 |
1st Row - Node
3rd Row - Time
How many weeks to build this unit? 25
Good Operation Manager will finish it earlier - maybe 15
No compromising quality
Done in 6 steps:
1 – Define Project
2 – Predecessor Table
3 – Time Table
4 – Network Diagram
5 – Forward Pass (calculate ES and EF – “the earlier you finish, the sooner I’ll start”).
Start from beginning to end
Goes with early start, EF
6 – Backward Pass (calculate LS and LF)
Late start, late finish
7 – Critical Path and Slack
5 & 6 are hardest
Examples:
Finished @ 9:42 PM